Key Dates

The SCGSR Program Key Dates are noted below. At the submission deadline (shown in red), the online application system will close after which no additional materials will be accepted. The online application system closes at 5:00 PM Eastern Time, so please plan accordingly.

SCGSR Project Periods

2020 Solicitation 2

2021 Solicitation 1

2021 Solicitation 2***

On-line Application Opens

August 20, 2020

February 9, 2021

August 2021

Applications Due November 12, 2020
5:00PM ET
May 5, 2021
5:00PM ET
November 2021
Offer Notification
Period Begins on or around

April/May 2021

August/September 2021

April/May 2022

Earliest* Start Date for
Proposed Project Periods

June 14, 2021

November 8, 2021

June 6, 2022

Latest** Start Date for
Proposed Project Periods

October 4, 2021

March 7, 2022