1.0 Introduction
This subject area provides the Office of Science (SC) Corporate Operating Experience/Lessons Learned (OPEX/LL) Program with the tools to monitor the relevant operating information of the entire corporate landscape, produce effective media for communicating relevant lessons learned, distribute the media to where it is needed, and evaluate the effectiveness of information distributed.
OPEX/LL programs involve examining and sharing good work practices, innovative approaches, or negative experiences to promote application of best practices or prevent recurrence of negative events.
This program provides for the systematic review, identification, collection, screening, evaluation, and dissemination of operating experience from sources both internal and external to the U.S. Department of Energy (DOE). The SC Lead Program Coordinator, Program Coordinators, and other OPEX/LL Coordinators ensure lessons learned are incorporated into training, maintenance and work planning, operations, and design and construction.
2.0Contents
Procedure | Procedure Content |
---|---|
Procedure 1. Implementing the Operating Experience/Lessons Learned (OPEX/LL) Program and Network of Contacts |
|
Procedure 2. Oversight of Federal and Contractor Operating Experience/Lessons Learned (OPEX/LL) Programs |
|
4.0 Related Information
-
DEAR Clause 970.5203-2, Performance Improvement and Collaboration
-
DOE O 151.1D, Change 1, Comprehensive Emergency Management System
-
DOE O 225.1B, Accident Investigations
-
DOE O 231.1B, Admin. Change 1, Environment, Safety and Health Reporting
-
DOE O 232.2A, Change 1, Occurrence Reporting and Processing of Operations Information
-
DOE O 413.3B, Change 5, Program and Project Management for the Acquisition of Capital Assets
-
DOE O 450.2, Change 1, Integrated Safety Management
-
DOE G 450.4‑1C, Integrated Safety Management System Guide
-
DOE‑STD‑7501‑99, The DOE Corporate Lessons Learned Program
-
Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 2004-1, Oversight of Complex, High-Hazard Nuclear Operations, dated May 21, 2004
-
Institute for Nuclear Power Operations (INPO) 94‑001, Significant Event Evaluation and Information Network (SEE-IN) Program Description
-
INPO 97‑001, Guidelines for the Use of Operating Experience
-
Nuclear Regulatory Commission (NRC) NUREG‑0737, Clarification of TMI Action Plan Requirements, Item I.C.5, "Procedures for Feedback of Operating Experience to Plant Staff"
-
NRC NUREG‑0933, A Prioritization of Generic Safety Issues, Task I.E., "Analysis and Dissemination of Operating Experience"
-
DOE Implementation Plan to Improve Oversight of Nuclear Operations, Revision 1, dated June 2005
-
SC Corporate Operating Experience/Lessons Learned (OPEX/LL) Coordinators
5.0 Requirements
Document | Title | Requirement Decision Record |
---|---|---|
10 CFR 830, Subpart A | Quality Assurance Requirements | Completed |
DOE O 210.2A | DOE Corporate Operating Experience Program | Completed |