1.0 Applicability
This procedure is applicable to Office of Science (SC) personnel involved in development, revision, or approval of the SC Functions, Responsibilities, and Authorities (FRA) documents.
2.0 Required Procedure
Step 1 |
The Environment, Safety, and Health (ES&H) Management System Owner (MSO) assigns a Lead to annually (or more often if needed) review the SC FRA and proposes revisions, if needed. |
Step 2 |
If needed, the Lead forms a team to revise the SC FRA. |
Step 3 |
The Lead or the Team performs the following:
|
Step 4 |
The Lead provides the proposed revised SC FRA to the Office of Science Management System (SCMS) Operations Center for review and comment. NOTE: The Lead discusses the proposed revision with the ES&H MSO prior to sending to the SCMS Operations Center. |
Step 5 |
The SCMS Operations Center sends the proposed revised SC FRA for review and comment to the appropriate SC personnel (e.g., the Field Elements and Program Offices). NOTE: After comment resolution is complete, the SCMS Operations Center sends the comment resolution response to the commenters. |
Step 6 |
The Lead or Team performs comment resolution, finalizes changes to the proposed revised SC FRA, and transmits to the ES&H MSO. |
Step 7 | The ES&H MSO reviews and concurs with the SC FRA. |
Step 8 |
The ES&H MSO provides the revised SC FRA to the SC Headquarters (HQ) Deputy Director for Field Operations (SC‑3). |
Step 9 |
SC‑3 concurs and obtains concurrence from the SC HQ Deputy Director for Science Programs (SC‑2). |
Step 10 | After concurrence by both SC‑3 and SC‑2, the SC‑3 forwards the SC FRA to the Director, Office of Science, (SC‑1) for approval. |
Step 11 | SC‑1 approves the revised SC FRA and forwards the approved SC FRA to the ES&H MSO. |
Step 12 | The ES&H MSO forwards approved SC FRA to the SCMS Operations Center. |
Step 13 | The SCMS Operations Center publishes the SC FRA and sends an email notification to the appropriate SC personnel. |
3.0 References
-
DOE O 450.2, Change 1, Integrated Safety Management
-
DOE P 450.4A, Change 1, Safety Management System Policy
-
DOE G 450.4-1C, Integrated Safety Management System Guide
- SC Environment, Safety, and Health Functions, Responsibilities, and Authorities Document Program Description